Complete implementation of the design, administrative and approval procedures, construction, and commissioning of a ground-mounted photovoltaic power plant with an installed capacity of 12,500 kWp, connected to the 20 kV power distribution grid.
Key technical parameters:
• Location: Krivodol, Vratsa region, Bulgaria
• Solar modules: Bifacial, Seraphim Solar
• Mounting structure: ERL Solar Mounting Systems, hot-dip galvanized steel
• Inverters: Huawei
• Transformer stations: Huawei
• Construction period: 4 months